This just in from Steve Spehn: Everything remains on schedule at the Arts Union project. The demolition
> is on track. Once the adjoining gym wall that will
> become a temporary exterior wall is shored up the rest of
> the cafeteria and north entry space will come down.
> The old boiler room and its stack have been demolished
> (The 1910 smoke stack will stay) Site work and utilities
> work will follow and we will begin footings and
> foundations. Abatement work is occurring in the 1910
> and 1934 building and will be completed mid-July. We
> will see more activity starting the end of July with
> interior renovation. Ed